Учебное пособие к курсовому и дипломному проектированию строительных процессов при возведении подземной части здания


Selection of vehicles for the construction of excavations and trenches



бет32/62
Дата31.12.2021
өлшемі12,75 Mb.
#22189
түріУчебное пособие
1   ...   28   29   30   31   32   33   34   35   ...   62
Байланысты:
Методическое указание по выполнению работы-converted

12. Selection of vehicles for the construction of excavations and trenches
As a set of equipment for haulage of extra soil out of pit (trench) and ensuring of joint work with excavator to be chosen dump trucks. Dump trucks are selected by two parameters: the capacity of the body and carrying capacity. Carrying capacity and brand of dump truck are shown in (Annex №1. table 12).

The solid soil volume in excavator bucket is determined:


𝑉𝑏𝑢𝑐𝑘 𝐶𝑓

𝑉𝑠𝑜𝑖𝑙 = 𝐶𝑓𝑟 ,

where, 𝑉𝑏𝑢𝑐𝑘–accepted volume of excavator bucket, 𝑚3;

𝐶𝑓–bucket filling factor: for front shovel from 1 to 1,25; the backhoe – from 0,8 to 1;

𝐶𝑓𝑟– Initial increase soil volume later

разрыхления грунта(прилож. №1. табл.1).

Определяют массу грунта в ковше экскаватора:


𝑄 = 𝑉гр ∙ 𝒱
где, 𝒱 средняя плотность грунта (по ЕНиР), кг/м3, для:

  • глины–1800 кг/м3;

  • супесь–2300 кг/м3;

  • песок–1800 кг/м3;

  • суглинок–2300 кг/м3;

  • гравий–1850 кг/м3;

  • лёсс–1600 кг/м3.

  • другое–2500 кг/м3.

Количество ковшей грунта, загружаемых в кузов автосамосвала:
𝑛 = П,

𝑄

где, П – грузоподъемность автосамосвала (прилож. №1. табл.12,14).



Определяют объем грунта в плотном теле, загружаемый в кузов автосамосвала:
𝑉 = 𝑉гр ∙ 𝑛.
Подсчитываем продолжительность одного цикла работы автосамосвала:
Т = 𝑡 + 60𝐿 + 𝑡 + 60𝐿 + 𝑡 ,

ц 𝑛 𝑉𝑟 𝑝 𝑉𝑛 м


где tn– время погрузки грунта (мин.), определяемое по формуле:
𝑉 ∙ 𝐻вр ∙ 60

𝑡𝑛 = 100 ,

developments (annex.№1.tab.1).
The soil volume in excavator bucket is determined:
𝑄 = 𝑉𝑠𝑜𝑖𝑙 ∙ 𝒱

where, 𝒱average soil density (on ENIR), kg/m3, for:



  • clays–1800 kg/m3;

  • sandy loam–2300 kg/m3;

  • sand–1800 kg/m3;

  • oam–2300 kg/m3;

  • gravel–1850 kg/m3;

  • loess–1600 kg/m3.

  • another–2500 kg/m3

Number of soil buckets, loaded into dump truck body:
𝑛 = 𝑃,

𝑄

where, P– truck carrying capacity (annex.№1. tab.12,14).



The solid soil volume in excavator bucket, loaded into dump truck body is determined:
𝑉 = 𝑉𝑠𝑜𝑖𝑙 ∙ 𝑛.

The duration of one work cycle of the truck is calculated:

Т = 𝑡 + 60𝐿 + 𝑡 + 60𝐿 + 𝑡 ,

𝑐 𝑙 𝑉𝑟 𝑝 𝑉𝑛 𝑚


where, tl– time of soil loading (min.) determined by a formula:
𝑡 = 𝑉 ∙ 𝑁𝑡𝑚 ∙ 60,

𝑙 100




где, 𝐻вр – норма машинного времени по ЕНиР (прилож. №1 табл.22);
𝐿 – расстояние транспортировки грунта, км(по заданию);

𝑉𝑟– средняя скорость автосамосвала в груженном состоянии, км/ч, (прилож. №1. табл.16);

𝑉𝑛 – средняя скорость автобамосвала в порожнем состоянии (25–30 км/ч);

𝑡𝑝– продолжительность разгрузки, (прилож. №1 табл.16);



𝑡м – время вспомогательных

операций (время установки под погрузку, под разгрузку, ожидание у эксковатора, пропуск встречного самосвала), мин. (прилож. №1. табл.16).

Требуемое количество автосамосвалов:

𝑁 = Тц



𝑡𝑛

Число N округляют до ближайшего наименьшего целого целого числа, учитывая перевыполнение сменного задания при работе экскаватора.