During trench excavation, removal of the top soil to be implemented at the area (only for the trench):
𝑆а = (10 + 𝑙1) ∗ (10 + 𝑙2), (𝑚2)
where,𝑙1𝑠.𝑡– the trench length at the top, m (determined per the scheme);
𝑙2𝑠.𝑡– the trench width at the top, m. (determined per the scheme);
The total volume of top soil removal is calculated by the formula (for the pit and the trench):
𝑉𝑠.𝑟=𝑆1(а)x0,15m, (𝑚3)
7.3.Разработка грунта в котловане и траншеи съезда в котлован
Определение объема котлована.
𝑉𝑘 =h/6[(2𝑙1п.н+𝑙1п.в) · 𝑙2п.н+ (2𝑙1п.в+𝑙1п.н)·𝑙2п.в], (м3)
где,ℎ – глубина котлована, м;
Объем земляных работ устройству траншеи съезда в котлован подсчитывается по формуле:
𝑉 = β̍ 𝑏∙ℎ2 + ℎ3∙𝑚
тр.с. ( 2 3 )
|
7.3. Soil excavation in the pit and trench access to the pit
Pit volume determination.
𝑉𝑝=h/6·[(2𝑙1𝑠.𝑏 +𝑙2𝑠.𝑡)𝑙2𝑠.𝑏.+(2𝑙1𝑠.𝑡.+
𝑙1𝑠.𝑏 )·𝑙2𝑠.𝑡 ], (𝑚3)
where, h– depth of pit, m.
Earthworks quantity of the trench access to the pit is calculated by the formula (only for pit):
𝑏∙ℎ2 ℎ3∙𝑚
𝑉tr.a. = β̍( + )
2 3
|
где, β– коэффициент заложения дна
въездной траншеи, β=100;
𝑖
𝑖 – уклон съезда, % (для проекта
можно принять 10% или I:10=10);
ℎ – глубина котлована, м;
b – ширина траншеи съезда по дну, принимается самостоятельно и равняется 3,5 (с односторонним движением) или 6 (при двустороннем движении), м;
m – коэффициент заложения откосов, (прилож. №1. табл.2).
Все грунты для обратной засыпки, служащие в дальнейшем основаниемдля фундаментов под оборудование, полов, отмостки, подъездных путей, должны уплотняться. При определении толщины отсыпаемых и уплотняемых слоев количества проходок грунтоуплотняющих средств целесообразно выполнять по ЕНиР.
|