Тоо «Tenaz Management» 060002, Республика Казахстан


November 2017 — April 2018 - DOOSAN HEAVY INDUSTRIES & CONSTRUCTION LLP



бет5/8
Дата22.06.2023
өлшемі0,52 Mb.
#102999
1   2   3   4   5   6   7   8
Байланысты:
Tenaz Arman Tasmagambetov

November 2017 — April 2018 - DOOSAN HEAVY INDUSTRIES & CONSTRUCTION LLP
Position - E&I Еngineer
Worked in Karabatan Power Plant Project comprises of 4 Gas Turbine Generators, 4 Heat Recovery Steam Generators and 2 Steam Turbine Generators. The plant will have agross capacity of 310MW. A fully Combined-Cycle Power Plant with an installed capacity of 310MW at 110kV and generating and distributing High Pressure steam for Special Economic Zone “National Industrial Petrochemical Technopark

  • Ensure Quality of the work & fulfilling project requirements

  • Initiate corrective actions for any raised non-conformance, and implement a preventive action plan to prevent the re-occurrence of non-conformance

  • Electrical and Instrumentation installation works 110kV Substation

  • Power transformers (115/11kV Step-Up Transformers; 110/10.5kV Step-Down Transformers; 10/0.72kV LV TR ; 10/0.42kV LV TR)

  • Auxiliary distribution system (10KV MV SWITCHGEAR ;690V LV Switchgear; 400V LV switchgear; 400V

MCC; 230V Distribution Board)

  • 110V DC DC & 230V AC UPS system; BATTERY

  • Protection relay system

  • Power and electrical control cables

  • Cable raceways (Cable Trench; Electrical Duct Banks; Cable trays; Hot dip galvanized steel conduits; PVC

conduits; Flexible conduits)

  • Lighting and Small power system

  • Grounding and Lightning protection system

  • Telecommunication System

  • Motors

  • Installation Procedure & Manual of Crane & Hoist

  • Coordinating all manpower and materials

  • Monitoring the construction plan; including schedule; quality report



June 2017 — November 2017 - GATE LLP via Fircroft Engineering Services LLP/ FGP Project


Достарыңызбен бөлісу:
1   2   3   4   5   6   7   8




©emirsaba.org 2024
әкімшілігінің қараңыз

    Басты бет